The first phase of the Downtown Arcadia Revitalization Study has been completed by Willdan Associates, engineers, architects and planners. A public meeting has been scheduled for Tuesday at 8:30 A.M. in the council chambers at City Hall to present to Arcadians in general and downtown merchants and property owners in particular the consultants' preliminary findings.

https://arcadiahistory.andornot.com/en/permalink/newspaper1298
Newspaper
Arcadia Tribune p A-1
Date
July 29, 1984
Newspaper
Arcadia Tribune p A-1
Date
July 29, 1984
Subjects
Community Redevelopment
Item ID
1297AN
Collection
Newspaper Index
Less detail

The revamped downtown debuts today with new streets, sidewalks, benches, palm trees and an all-day street fair. This marks the completion of the Downtown 2000 construction project.

https://arcadiahistory.andornot.com/en/permalink/newspaper5818
Newspaper
Pasadena Star News
Date
March 30, 1996
Pages
p. A-3 photo
Newspaper
Pasadena Star News
Date
March 30, 1996
Pages
p. A-3 photo
Subjects
Community Redevelopment
Item ID
5663AN
Collection
Newspaper Index
Less detail

Construction crews began digging up streets and sidewalks along Huntington Drive in June for the City's Downtown 2000 Renovation Project. Traffic jams, frustrated customers and declining sales have been the result.

https://arcadiahistory.andornot.com/en/permalink/newspaper4849
Newspaper
Pasadena Star News Hometown
Date
August 10, 1995
Pages
p. H1
Newspaper
Pasadena Star News Hometown
Date
August 10, 1995
Pages
p. H1
Subjects
Community Redevelopment
Item ID
4725AN
Collection
Newspaper Index
Less detail

Article discusses progress of redevelopment project on Huntington Drive east of First Avenue. Completion may be ten years away.

https://arcadiahistory.andornot.com/en/permalink/newspaper1275
Newspaper
Arcadia Tribune
Date
July 24, 1980
Pages
p. A-1
Newspaper
Arcadia Tribune
Date
July 24, 1980
Pages
p. A-1
Subjects
Community Redevelopment
Item ID
1274AN
Collection
Newspaper Index
Less detail

The $4.1 million Downtown 2000 plan will restore the area along Huntington Drive from Santa Clara to 5th Avenue, as well as on 1st Ave. The project should start in June and be completed by the fall racing season.

https://arcadiahistory.andornot.com/en/permalink/newspaper4477
Newspaper
Los Angeles Times
Date
January 26, 1995
Pages
p. J-3 map
Newspaper
Los Angeles Times
Date
January 26, 1995
Pages
p. J-3 map
Subjects
Community Redevelopment
Item ID
4353AN
Collection
Newspaper Index
Less detail

Between August 11 and September 30, the city will install brick sidewalks on Huntington Drive between 2nd Avenue and Santa Clara Street as the first major phase of Arcadia's downtown revitalization project.

https://arcadiahistory.andornot.com/en/permalink/newspaper1327
Newspaper
Arcadia Tribune
Date
August 10, 1986
Pages
p. A-2
Newspaper
Arcadia Tribune
Date
August 10, 1986
Pages
p. A-2
Subjects
Community Redevelopment
Item ID
1326AN
Collection
Newspaper Index
Less detail

On First Avenue, business owners are elated with the way construction related to the city's Downtown 2000 has worked out.

https://arcadiahistory.andornot.com/en/permalink/newspaper5663
Newspaper
Pasadena Star News
Date
December 4, 1995
Pages
p. A1
Newspaper
Pasadena Star News
Date
December 4, 1995
Pages
p. A1
Subjects
Streets - First Avenue
Community Redevelopment - Downtown 2000
Item ID
5514AN
Collection
Newspaper Index
Less detail

Downtown 2000, the $4 million revitalization project, will primarily affect Huntington Drive and First Ave. Huntington Drive will have more landscaping and lighting, while First Ave. will have angled parking and landscaping to be more pedestrian oriented.

https://arcadiahistory.andornot.com/en/permalink/newspaper4480
Newspaper
Sierra Madre News
Date
January 19, 1995
Pages
p. 13
Newspaper
Sierra Madre News
Date
January 19, 1995
Pages
p. 13
Subjects
Community Redevelopment
Item ID
4356AN
Collection
Newspaper Index
Less detail

Continuation of answers from the City to the most frequently asked questions about the Downtown 2000 revitalization project.

https://arcadiahistory.andornot.com/en/permalink/newspaper5709
Newspaper
Sierra Madre News
Date
January 11, 1996
Pages
p. 8
Newspaper
Sierra Madre News
Date
January 11, 1996
Pages
p. 8
Subjects
Community Redevelopment
Item ID
5560AN
Collection
Newspaper Index
Less detail

The City of Arcadia answers some of the most frequently asked questions about the Downtown 2000 revitalization project.

https://arcadiahistory.andornot.com/en/permalink/newspaper5716
Newspaper
Sierra Madre News
Date
January 4, 1996
Pages
p. 8
Newspaper
Sierra Madre News
Date
January 4, 1996
Pages
p. 8
Subjects
Community Redevelopment
Item ID
5567AN
Collection
Newspaper Index
Less detail

A strike involving the operating engineers union has brought the progress of the Downtown 2000 project to a temporary halt.

https://arcadiahistory.andornot.com/en/permalink/newspaper4832
Newspaper
Sierra Madre News
Date
August 17, 1995
Pages
p. 7
Newspaper
Sierra Madre News
Date
August 17, 1995
Pages
p. 7
Subjects
Community Redevelopment
Item ID
4708AN
Collection
Newspaper Index
Less detail

City officials determined that Sulley-Miller is in gross violation of the Downtown 2000 project. In a unanimous vote, city officials terminated this company as contractor for the project.

https://arcadiahistory.andornot.com/en/permalink/newspaper5490
Newspaper
Sierra Madre News
Date
October 5, 1995
Pages
p. 7
Newspaper
Sierra Madre News
Date
October 5, 1995
Pages
p. 7
Subjects
Community Redevelopment
Item ID
5350AN
Collection
Newspaper Index
Less detail

City Council approved lending the city redevelopment agency $1.2 million Tuesday to cover additional cost overruns with Downtown 2000 and other projects.

https://arcadiahistory.andornot.com/en/permalink/newspaper6593
Newspaper
Pasadena Star News
Date
July 17, 1996
Pages
p. A1
Newspaper
Pasadena Star News
Date
July 17, 1996
Pages
p. A1
Subjects
Community Redevelopment
Item ID
6406AN
Collection
Newspaper Index
Less detail

City Council members voted 4-0 to change lighting plans and add a new storm drain system to the Huntington Drive streetscape project, changing the cost from $4.1 to $5.6 million.

https://arcadiahistory.andornot.com/en/permalink/newspaper4486
Newspaper
Pasadena Star News
Date
February 16, 1995
Pages
p. H-3
Newspaper
Pasadena Star News
Date
February 16, 1995
Pages
p. H-3
Subjects
Community Redevelopment
Item ID
4362AN
Collection
Newspaper Index
Less detail

The Arcadia City Council plans to seek more than $1 million in damages against its original contractor for cost overruns in the City's Downtown 2000 revitalization project.

https://arcadiahistory.andornot.com/en/permalink/newspaper5639
Newspaper
Pasadena Star News
Date
November 23, 1995
Pages
p. A1
Newspaper
Pasadena Star News
Date
November 23, 1995
Pages
p. A1
Subjects
Community Redevelopment
Item ID
5490AN
Collection
Newspaper Index
Less detail

Arcadia City Council voted 4-0 in favor of searching for a temporary contractor for the Downtown 2000 project. Striking workers have caused delays and fears of future health problems.

https://arcadiahistory.andornot.com/en/permalink/newspaper4823
Newspaper
Pasadena Star News
Date
August 23, 1995
Pages
p. A3
Newspaper
Pasadena Star News
Date
August 23, 1995
Pages
p. A3
Subjects
Community Redevelopment
Item ID
4699AN
Collection
Newspaper Index
Less detail

Arcadia City Council may declare the Downtown 2000 construction project a potential health emergency in order to suspend it's contract with striking workers and hire another firm to do the work until the strike is over.

https://arcadiahistory.andornot.com/en/permalink/newspaper4828
Newspaper
Pasadena Star News
Date
August 20, 1995
Pages
p. A3
Newspaper
Pasadena Star News
Date
August 20, 1995
Pages
p. A3
Subjects
Community Redevelopment
Item ID
4704AN
Collection
Newspaper Index
Less detail

Downtown 2000, the redevelopment project that has served as a lightning rod for discontent at City Hall, received an Award of Excellence this week from the California Redevelopment Association.

https://arcadiahistory.andornot.com/en/permalink/newspaper18617
Newspaper
Pasadena Star News
Date
March 18, 2000
Pages
p. A3
Newspaper
Pasadena Star News
Date
March 18, 2000
Pages
p. A3
Subjects
Community Redevelopment - Downtown 2000
Item ID
18861AN
Collection
Newspaper Index
Less detail

The City will pay $1.25 million to the Sully Miller Contracting Co. to settle a breach-of-contract lawsuit the company filed after it was fired from the Downtown 2000 project.

https://arcadiahistory.andornot.com/en/permalink/newspaper8900
Newspaper
Pasadena Star News
Date
February 7, 1997
Pages
p. A3
Newspaper
Pasadena Star News
Date
February 7, 1997
Pages
p. A3
Subjects
Community Redevelopment - Downtown 2000
Item ID
8855AN
Collection
Newspaper Index
Less detail

After two weeks of delays, construction work has resumed along the downtown stretch of Huntington Drive and First Ave. City officials have hired a new contractor.

https://arcadiahistory.andornot.com/en/permalink/newspaper4819
Newspaper
Pasadena Star News
Date
August 31, 1995
Pages
p. A2
Newspaper
Pasadena Star News
Date
August 31, 1995
Pages
p. A2
Subjects
Community Redevelopment
Item ID
4695AN
Collection
Newspaper Index
Less detail

20 records – page 1 of 1.