Foothill Gold Line construction update. The Gold Line light rail from Pasadena to Azusa has now surpassed 85% complete. Overview of bridge construction, track completion, grade crossings, and train testing. Substantial completion of entire project remains on schedule for late September 2015, when the project as a whole will be turned over to Metro for pre-revenue service. Metro will decide when the line will open for passenger service.