Construction of 210 Freeway Gold Line bridge near Santa Anita Avenue in Arcadia, is nearing completion. Work should be complete in 3 months. Nighttime closures of the freeway will cause delays. The bridge will allow connection between Pasadena's Sierra Madre Villa Station and the future Arcadia Station. It is the first piece of the $735 million, 11.5 mile Pasadena-to-Azusa Metro Gold Line Foothill Extension.