Metro Gold Line Bridge, which represents woven baskets, over the 210 Foothill Freeway near Baldwin Avenue in Arcadia, gets its fifth award. The latest one was "Best Project in Southern California" for highways and bridges from Engineering News-Record, a national trade journal on construction and design. The award was presented to Habib Balian, CEO of Metro Gold Line Foothill Extension Construction Authority. Sharing in the award was AECOM, the lead architectural firm that implemented the concept from artist Andrew Leicester and Skanska USA, the construction contractor.
Foothill Gold Line construction update. The Gold Line light rail from Pasadena to Azusa has now surpassed 85% complete. Overview of bridge construction, track completion, grade crossings, and train testing. Substantial completion of entire project remains on schedule for late September 2015, when the project as a whole will be turned over to Metro for pre-revenue service. Metro will decide when the line will open for passenger service.
Closures of southbound Baldwin Avenue in Arcadia starting July 6 for approximately 2 weeks. Crews will be installing underground duct banks and electrical vaults as part of the 11.5 mile Metro Gold Line Foothill Extension Light Rail project.
Trainspotting in Arcadia. First tests of Gold Line light rail between Pasadena and Azusa start. Metro Gold Line Foothill Extension conducted the first of many clearance tests involving actual Metro Gold Line train from Sierra Madre Villa Station (in Pasadena) to Azusa. The train was a $4 million Ansaldo Breda P2250 with specialized gear to test clearances, wheel/rail interface, rail switches, and Overhead Catenary System.
Gold Line Bridge wins prestigious architectural design recognition from ArchDaily in its Top 100 Projects of the last decade. The "bridge baskets" were designed by artist Andrew Leicester.
The Metro Gold Line Foothill Extension Construction Authority opened bidding yesterday on Phase 2A of the light rail's extension toward Azusa, which would make a stop in Arcadia. The project is estimated to cost more than $450 million with a completion date in 2017. Measure R guarantees full funding for the Gold Line Extension minus a gap of $500,000. With possible help from a private investment, the completion could be moved up to 2013.
Closure of Santa Anita Avenue today begins seven months of bridge construction in Arcadia. Crews will begin constructing a new bridge over Santa Anita Avenue at the railroad crossing in Arcadia, as part of the 11.5 mile Metro Gold Line Foothill Extension light rail project.
Four day full closure of Huntington Drive and Second Avenue intersection in Arcadia begins Friday, August 8, for Gold Line Foothill Extension light rail construction.
All aboard: Arcadia gets into training. The Metro Gold Line Station in Arcadia will have a grand opening on Saturday, March 5. The light rail Foothill Extension from Pasadena to Azusa will be offering free rides on March 5.
The 11.5 mile light rail Gold Line extension from Pasadena to Azusa was awarded to Foothill Transit Constructors. Kiewit-Parsons, a joint venture company, will design and build the project. Funding comes from Measure R.
First Avenue at Santa Clara Street in Arcadia closed September 9, 2013 through February, 2014 for construction of grade crossing improvements, as part of the Metro Gold Line Foothill Extension light rail project in Arcadia. Also, to construct the parking structure and transit plaza adjacent to the crossing, Front Street between Santa Clara Street and Saint Joseph Street, will be permanently closing in September.
Lack of train cars may delay the openings of the Expo Line Phase 2 from Culver City to Santa Monica and the Gold Line Foothill Extension from Pasadena to Azusa. Metro reports delivery of rail cars won't be complete until January 2017, while construction of the extensions should be done July/August (Expo) and late September (Gold Line), of 2015. The builder of the train cars is Kinkisharyo International, a Japanese company that is assembling the light rail trains in Palmdale, California. The Expo Line needs 42 cars and the Gold Line needs 15.
The county Metropolitan Transportation Authority will sell naming rights to all rail lines, bus lines, and transit stations, such as the Gold Line Monrovia Station (in photo) and Foothill Gold Line Arcadia Station (in photo). The Corporate Sponsorship/Naming Rights Program was approved by the Metro board. CEO Phil Washington wants to stretch revenue; board member objects to commercialization.
Gold Line construction moving forward on schedule. First Avenue in Arcadia to open by the end of March. See hard copy VF "Railroads-Light Rail-Metro Gold Line."
Metro Gold Line Foothill Extension moves ahead. Contractor Kiewit Parsons is given full "notice to proceed" to build the 11.5 mile route for the light rail train from Pasadena to Azusa, with a stop in Arcadia, by a planned 2015 completion date.
Metro Gold Line Foothill Extension Construction Authority announced that structural work is complete for Gold Line Bridge over Interstate 210 Freeway. "The bridge can now stand on its own," said Construction Authority CEO Habib F. Balian. The bridge is a 584-linear foot, $18.6 million rail bridge that helps extend the Gold Line from Pasadena to Azusa, in this first segment.
Metro responds to concerns over paid parking at Arcadia Gold Line Station. It costs $3 to park there but it had been free. Now that there is a cost to parking at Arcadia Station, there are more open spaces and this was Metro's anticipated and desired effect.
The Metro Gold Line Foothill Extension Construction Authority Board of Directors adopts new policies to enhance agency's transparency and accountability.
Metro amps up security to protect Arcadia, Monrovia and Pasadena public transportation residents. Metro has added local Los Angeles Police Department law enforcement to patrol the rail and bus lines.
Train testing underway throughout summer along the Foothill Gold Line light rail project from Pasadena to Azusa. Testing is currently taking place in Duarte and portions of Irwindale, and will expand to the cities of Pasadena, Arcadia, Monrovia and Azusa over the next several months.