Construction of 210 Freeway Gold Line bridge near Santa Anita Avenue in Arcadia, is nearing completion. Work should be complete in 3 months. Nighttime closures of the freeway will cause delays. The bridge will allow connection between Pasadena's Sierra Madre Villa Station and the future Arcadia Station. It is the first piece of the $735 million, 11.5 mile Pasadena-to-Azusa Metro Gold Line Foothill Extension.
Gold Line bridge across the 210 Freeway just west of Santa Anita Avenue is underway. There is a temporary support structure across the lanes which allows trucks under 15 feet tall to pass freely. When the structure is complete, the Gold Line Construction Authority says the height allowance will be 19 feet. The $18.6 million, 584-foot Gold Line Bridge, the first component of the 11.5 mile Pasadena to Azusa Metro Gold Line Foothill Extension, started last summer and expected to be completed later this year.
A Metro Gold Line deal to purchase land in Monrovia for a maintenance yard for $56 million, from George Brokate, a Marine veteran from Newport Beach, has been reached. This cleared the last major obstacle to the $735 million Pasadena to Azusa Metro Gold Line Foothill Extension. Photo shows the Gold Line bridge over the 210 Freeway in Arcadia under construction.
Metro Gold Line Foothill Extension Construction Authority announced that structural work is complete for Gold Line Bridge over Interstate 210 Freeway. "The bridge can now stand on its own," said Construction Authority CEO Habib F. Balian. The bridge is a 584-linear foot, $18.6 million rail bridge that helps extend the Gold Line from Pasadena to Azusa, in this first segment.
Work continues on Metro Gold Line Foothill Extension project. Workers installed a 130-foot-high steel cage that will make up a portion of a rapid transit bridge spanning the eastbound 210 Freeway between Baldwin Avenue and Santa Anita Avenue. When complete, the 584-foot-long, $18.6 million Metro Gold Line bridge will be buttressed by columns designed to resemble Native American baskets. The bridge work is expected to be completed in the summer of 2012, while the entire 11.5-mile extension is due to be finished 2015. The bridge contractor is Skanska USA Civil. Construction of the rest of the line may be delayed due to problems with Monrovia's Redevelopment Agency.
Gold Line bridge construction work on track; more eastbound 210 Freeway closures ahead. Motorists can expect up to 14 more full-lane, night closures in the coming weeks as workers complete a temporary structure needed to support the $18.6 million Gold Line Bridge. The bridge is expected to be completed next summer.
A sculptural 584-foot Metro Gold Line bridge, that will span the eastbound 210 Freeway, is under construction now. The $18.6 million bridge will be a dramatic gateway to the San Gabriel Valley. The bridge builder is Skanska USA Civil. The bridge's design concept of Native American baskets was designed by artist Andrew Leicester. The bridge should be completed in summer 2012. The bridge will have a built-in technology that can gauge damage to underground pilings after an earthquake. The entire 11.5 mile eastward Gold Line Foothill Extension through Arcadia, Monrovia, Duarte, Irwindale and Azusa is due to be finished in 2015.
Completion of the Gold Line Bridge over the 210 Foothill Freeway in Arcadia is celebrated. The $18.6 million bridge, completed on time and on budget, is only one element of the $1.2 billion eastward extension of the Gold Line through Arcadia, Monrovia, Duarte, Irwindale, and Azusa. Andrew Leicester is the artist and designer of the bridge baskets.
Gold Line Bridge over the 210 Foothill Freeway is progressing and artist Andrew Leicester, creator of the woven Native American basket design, approves. The final details of the $18.6 million bridge, including lighting and landscaping, will be completed next month.
Closure of Santa Anita Avenue today begins seven months of bridge construction in Arcadia. Crews will begin constructing a new bridge over Santa Anita Avenue at the railroad crossing in Arcadia, as part of the 11.5 mile Metro Gold Line Foothill Extension light rail project.
Metro to improve 210 Freeway barriers, after a series of crashes over the last 2 years involved cars and trucks landing on the Gold Line tracks. Metro plans to install taller, stronger barriers and a detection system on 6 miles of right-of-way down the middle of the 210 Freeway in Pasadena and Arcadia.
Construction of the Metro Gold Line Foothill Extension bridge, that will span the 210 Freeway, has begun. Preparation of the giant column supports included drilling over 100 feet into the ground. The 584-foot Gold Line bridge will take shape by December. It replaces an old railroad bridge across the freeway, which was built about 1969 and torn down in 1997, said Gary Baker, director of construction for the Metro Gold Line Foothill Extension Construction Authority. The bridge's design has been controversial, as some say it is not representative of the origins of the area. The entire bridge is slated to be finished summer 2012.
Officials lobby for Gold Line extension funding. $764 million is needed to finish the final segment of the extension from Azusa-to-Claremont. The Gold Line Construction Authority board this week approved an updated expense plan for the entire 23-mile Pasadena-to-Claremont extension of nearly $1.6 billion, of which $810 million has already been allocated, with full completion planned for 2021. The Metropolitan Transportation Authority has already funded the Gold Line's 11.5 mile, $750 million Pasadena-to-Azusa segment with Measure R revenues, but the $780 million Azusa-to-Claremont segment has yet to be funded.
Metro Gold Line Foothill Extension moves ahead. Contractor Kiewit Parsons is given full "notice to proceed" to build the 11.5 mile route for the light rail train from Pasadena to Azusa, with a stop in Arcadia, by a planned 2015 completion date.
Closures of southbound Baldwin Avenue in Arcadia starting July 6 for approximately 2 weeks. Crews will be installing underground duct banks and electrical vaults as part of the 11.5 mile Metro Gold Line Foothill Extension Light Rail project.
Construction of the Gold Line Bridge in Arcadia, over the 210 Freeway, will cause eight more full overnight eastbound lane closures through March 17, between Rosemead Boulevard and Santa Anita Avenue.
Metro Gold Line Foothill train set to roll on March 5. The 11.5 mile extension from East Pasadena's Sierra Madre Villa Station to Azusa/Glendora border is expected to have 13,600 riders per day and trains to arrive every 12 minutes. The new stations are Arcadia, Monrovia, Duarte/City of Hope, Irwindale, Azusa Downtown, and Azusa Pacific University.
Foothill Gold Line construction update. The Gold Line light rail from Pasadena to Azusa has now surpassed 85% complete. Overview of bridge construction, track completion, grade crossings, and train testing. Substantial completion of entire project remains on schedule for late September 2015, when the project as a whole will be turned over to Metro for pre-revenue service. Metro will decide when the line will open for passenger service.
Trainspotting in Arcadia. First tests of Gold Line light rail between Pasadena and Azusa start. Metro Gold Line Foothill Extension conducted the first of many clearance tests involving actual Metro Gold Line train from Sierra Madre Villa Station (in Pasadena) to Azusa. The train was a $4 million Ansaldo Breda P2250 with specialized gear to test clearances, wheel/rail interface, rail switches, and Overhead Catenary System.