2,100 cubic yards of concrete has been poured now and the 584-foot Gold Line Bridge is taking shape inside the wood forms above the eastbound lanes of the 210 Freeway.
The 11.5 mile light rail Gold Line extension from Pasadena to Azusa was awarded to Foothill Transit Constructors. Kiewit-Parsons, a joint venture company, will design and build the project. Funding comes from Measure R.
The abandoned rail bridge over Colorado Boulevard in Arcadia will be removed because it could not accommodate the two-track light rail system and the Gold Line Construction Authority determined it was more efficient and cost effective to remove the structure than to widen it or add a second structure directly adjacent to the ole one. Bridge demolition was the first significant construction effort for Foothill Transit Constructors (FTC) and the alignment project. The Construction Authority will have three open houses in the next two weeks to update the community.
After receiving intense pressure from San Gabriel Valley lawmakers, the county's transportation board, the MTA, finally put the Gold Line extension in its long-term plans. This opens up the possibility of federal funding for the project. With this commitment, the Metropolitan Transportation Authority (MTA) has agreed to provide day-to-day operational funding for the first phase of the Gold Line Foothill extension once it is completed.
All 14 at-grade rail crossings now complete for Foothill Gold Line, from Pasadena to Azusa. The at-grade crossing in Arcadia is at First Avenue and Santa Clara Street.
All aboard: Arcadia gets into training. The Metro Gold Line Station in Arcadia will have a grand opening on Saturday, March 5. The light rail Foothill Extension from Pasadena to Azusa will be offering free rides on March 5.
All aboard: Gold Line extension opened yesterday with free rides, and nearly 30,000 people jammed into the 6 new stations from Arcadia to Azusa. Photos of the grand opening.
Arcadia Transit Plaza dedication ceremony held November 6, 2014. It is located at 99 Santa Clara Street, at First Avenue, where the Gold Line Station in Arcadia is being built. It will serve as a transportation hub and a gathering space for the community. Many VIPs attended (photos).
Artist Andrew Leicester, 61, has been chosen to design a bridge meant to be an iconic gateway to the San Gabriel Valley along the Gold Line Foothill Extension. The bridge will cost an estimated $20-25 million to build. Leicester, who is based in Minneapolis, plans to incorporate artistic traditions from the Native American tribes of the San Gabriel Valley (Chumash and Gabrielenos a.k.a. Tongva), and references to the region's native animal and plant life, into a contemporary structure.
The city council has decided to appropriate $35,000 toward the design of a light rail bridge over Santa Anita Avenue. This is to pay for early design work needed for an environmental impact report. The bridge project is expected to cost the city $10.7 million which may come from a bond. The Construction Authority would pay $18.4 million bringing total bridge cost to $29.1 million.
Closure of Santa Anita Avenue today begins seven months of bridge construction in Arcadia. Crews will begin constructing a new bridge over Santa Anita Avenue at the railroad crossing in Arcadia, as part of the 11.5 mile Metro Gold Line Foothill Extension light rail project.
Closures of southbound Baldwin Avenue in Arcadia starting July 6 for approximately 2 weeks. Crews will be installing underground duct banks and electrical vaults as part of the 11.5 mile Metro Gold Line Foothill Extension Light Rail project.
Colorado Boulevard between Santa Anita Avenue and San Antonio Road will be closed for nearly 5 months to allow crews to build a bridge needed for Metro Gold Line Foothill Extension. The Colorado Boulevard bridge is one of three Gold Line bridges to be built on Arcadia streets. The stretch of Colorado Boulevard will be closed 24 hours/day, 7 days/week until April 30.
Completion of the Gold Line Bridge over the 210 Foothill Freeway in Arcadia is celebrated. The $18.6 million bridge, completed on time and on budget, is only one element of the $1.2 billion eastward extension of the Gold Line through Arcadia, Monrovia, Duarte, Irwindale, and Azusa. Andrew Leicester is the artist and designer of the bridge baskets.
Construction of 210 Freeway Gold Line bridge near Santa Anita Avenue in Arcadia, is nearing completion. Work should be complete in 3 months. Nighttime closures of the freeway will cause delays. The bridge will allow connection between Pasadena's Sierra Madre Villa Station and the future Arcadia Station. It is the first piece of the $735 million, 11.5 mile Pasadena-to-Azusa Metro Gold Line Foothill Extension.
Construction of the Gold Line Bridge in Arcadia, over the 210 Freeway, will cause eight more full overnight eastbound lane closures through March 17, between Rosemead Boulevard and Santa Anita Avenue.
Construction of the Gold Line Foothill Extension will create nearly 7000 new jobs and pump nearly $1 billion into the region's economy, according to a new study of the project.
Construction of the Metro Gold Line Foothill Extension bridge, that will span the 210 Freeway, has begun. Preparation of the giant column supports included drilling over 100 feet into the ground. The 584-foot Gold Line bridge will take shape by December. It replaces an old railroad bridge across the freeway, which was built about 1969 and torn down in 1997, said Gary Baker, director of construction for the Metro Gold Line Foothill Extension Construction Authority. The bridge's design has been controversial, as some say it is not representative of the origins of the area. The entire bridge is slated to be finished summer 2012.